Reading Schedule
Charts
A Barchart Schedule (see below) is the CPM Schedule expressed in a graphic form
with each task represented as a bar in a timescale. The numbered elements of
the chart are described below.

(1) Task ID (or Activity ID) - This number is only used for identification purposes.
(2) Task (or Description) - This
is the Activity Description.
(3) Work Days (or Original Duration)
- This is the total number of days originally planned to complete this task
often expressed in work-days.
(4) Start Date (or Early Start) -
This is the earliest planned start date of this task.
(5) Finish Date (or Early Finish)
- This is the earliest planned finish date of this task.
(6) Total Float - This is the total
number of days this activity can be delayed before it affects the project completion
date.
(7) Time Scale This is a calendar
expressed at the top and bottom of the chart so each task, expressed as a bar)
can be read as a period of time in the calendar of dates.
(8) Task Bar (or Activity Bar)
This is a graphic way of indicating each task or activity duration in a bar
chart form expressed in the Time Scale Calendar.