The Logic
Report is the
CPM Schedule expressed in a tabular form listing the information about the
task and their relationships.

Each column has information about the activity as follows:
1.
Activity
ID - The same identification number as the Task ID in the schedule.
2.
Original
Duration - The original number of workdays.
3.
Remaining
Duration – The remaining amount of workdays.
4.
(%) - The
percentage is of the activity that is complete.
5.
Predecessors/Successors
- Signifies whether the listed activity is a predecessor (PR) or successor
(SU) of this activity
6.
Signifies
the type of relationship between activities, such as FS – Finish to
start; SS – Start to start; FF – Finish to finish; SF –
Start to finish. This also indicates
the amount of lag associated with the relationship.
7.
Activity
Description – The same activity description as in the barchart schedule
8.
Early Start
– The earliest date this activity can start
9.
Early Finish
– The projected date the activity will complete if started on the Early
Start date.
10.
Late Start
– The latest this activity can start without impacting the end date.
11.
Late Finish
– The latest this activity can finish without impacting the end date.
12.
Total Float - The total number of
days this activity can be delayed before it affects the project completion
date.